Offshore Wind Rights

How developers obtain federal leases, state cable approvals, and local permits to build offshore wind farms.

Prof. Michael GerrardColumbia Law School
Duration: 2:32253 views

Key Takeaways

  • Offshore wind farms in federal waters require a lease from the Bureau of Ocean Energy Management, which awards leases through competitive auctions.
  • Export cables crossing state waters, generally the first three nautical miles from shore, need state approval and Army Corps permits, and onshore facilities need local approvals.
  • Since 2025, federal actions to halt offshore wind have faced repeated court challenges, and disputes over stop-work orders and lease cancellations are still being litigated.

Who owns the ocean floor off America's coasts, and how does a company get the right to build a wind farm there?

In this TalksOnLaw Brief, Joel Cohen talks with Michael Gerrard, Andrew Sabin Professor of Professional Practice at Columbia Law School and founder and faculty director of the Sabin Center for Climate Change Law, about the layers of federal, state, and local approval that an offshore wind project must clear.

Layers of Jurisdiction

Professor Gerrard explains that the offshore areas where large wind farms are built are owned by the federal government. The agency in charge is the Bureau of Ocean Energy Management, part of the Department of the Interior. He notes that permitting slowed during the first Trump administration and that he expected it to pick up under the Biden administration. Federal approval is only the start, though. Power cables must come ashore, and roughly the first three miles offshore are within state jurisdiction, so the state must grant authority for the cables, along with the Army Corps of Engineers. Once the project reaches land, the onshore facilities are largely a matter of local zoning.

Leasing by Auction

How do developers obtain the rights? Professor Gerrard explains that the Bureau of Ocean Energy Management holds auctions to lease offshore areas. On federal land, by contrast, the Bureau of Land Management, a different part of the Interior Department, holds auctions for the use of federal land for energy facilities.

The Block Island Example

At the time of the conversation, the only operating U.S. offshore wind farm was off Block Island, Rhode Island. Professor Gerrard credits local support: residents expected the small wind farm to lower their electricity rates, and the project obtained its approvals and was built. He predicted a large wave of development off Long Island, Massachusetts, and New Jersey, with all of those states strongly encouraging offshore wind.

What to Know Now

The legal architecture Professor Gerrard describes is unchanged, and some of the projects he anticipated were built: South Fork Wind, serving New York, began delivering power in 2024. Federal policy then reversed. A January 20, 2025 presidential memorandum withdrew offshore areas from new wind leasing and paused new approvals; BOEM later rescinded designated wind energy areas, and the Interior Department issued stop-work orders against projects under construction, including Revolution Wind in August 2025 and five Atlantic projects in December 2025, citing national security concerns. Courts pushed back. In December 2025 a federal court in Massachusetts vacated the pause on wind authorizations, and the government dropped its appeal in 2026; judges also enjoined the stop-work orders against all five projects. In 2026 the Interior Department reached agreements to cancel several leases in exchange for refunds and investments in other energy projects, and states have sued over those deals. The administration cites cost, reliability, and security concerns; states and developers point to approved leases, investments, and clean energy goals. Litigation continues.

Additional Resources

Statutes

Agency and Litigation Resources

  • Bureau of Ocean Energy Management, Renewable Energy (2026): BOEM's hub for offshore wind leasing, project approvals, and lease settlement notices.
  • New York v. Trump (D. Mass. 2025): Vacated the federal pause on wind energy authorizations as a violation of the Administrative Procedure Act.
  • Revolution Wind, LLC v. Burgum (D.D.C. 2026): Preliminary injunction blocking enforcement of a stop-work order against the Revolution Wind project.
  • Harvard Environmental and Energy Law Program, Federal Offshore Wind Deployment tracker (2026): A running timeline of offshore wind litigation and federal actions.